IBEDC and Bresson Sign N180Bn Magboro Power Plant Purchase Agreement With IBEDC

 Olushola Bello 

The first phase of Magboro Power Plant Kicked off  Monday 28th October 2024 with official signing and unveiling of the 30 MW Power purchase agreement between Bresson A S, Magboro  Power Company and Ibadan Electricity Distribution Company.

Customers around Magboro, Mowe are expected within 11 months to benefit from 24hours uninterrupted electricity supply as a result of the collaboration between Bresson and IBEDC  at competitive rates.

The Magboro plant designed as a 90 MW plant is expected to receive its first shipment of Titan 170 Solar Turbine by the end of April 2025.

In his remarks, Engr. Francis Agoha, the Acting Managing Director of IBEDC, emphasized that this partnership aligns with the federal government’s target of 6000 Mega Watts power projection  for 2024 and the company’s strategic goal of improving customer energy availability.

 “This agreement marks a significant milestone in our continuous efforts to ensure consistent and affordable power for the Magboro community and beyond,” he stated.

“We are committed to forging partnerships that foster progress and deliver lasting solutions to the power challenges faced by communities within our network.”

Magboro Power Company Limited, a respected independent power developer, will play a crucial role in this initiative.

Businessstandardsng.com/a strategic cross-reporting initiative with enterprisethrob.com

Related Articles

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Stay Connected

0FansLike
0FollowersFollow
0SubscribersSubscribe
- Advertisement -spot_img

Latest Articles